Skip Ribbon Commands
Skip to main content
Navigate Up

designdevelopmentsubmission - Copy.jpg

Information and Resources Regarding the New Quispamsis Elementary School

 

IMPORTANT!

The information presented has been adopted as the defined boundaries and enrollments will be based on the information provided on this page. Please review the street list as well as drawn boundaries below for more information.
  Click each tab heading to navigate through the available information.

A new 350 student elementary school for Quispamsis was announced in the 2012-2013 provincial budget.

  • Fall 2012
    • Department of Transportation and Infrastructure determined there is space to construct a two level 350 student K-5 school. The location was approved by the District Education Council (September 2012)
    • Educational Specifications document developed – led by Josh Nowlan, Senior Project Manager, Department of Education & Early Childhood Development.  This document is unique to each school project and outlines the size and use of the spaces in the school
    • Meetings with the Town of Quispamsis to look at growth, trends in housing starts.
    • Examination of enrolment trends and kindergarten registrations for 2012-13
  • Winter 2012
    • Educational specifications signed off by committee and approved by District Education Council and forwarded to Minister
    • Minister of Education Jody Carr & MLAs visited the site January 2013 and a sign was erected
  • Spring 2013
    • Adjacency drawings developed by the committee and Josh Nowlan
    • Transportation staff began to examine boundaries
  • Fall 2013
    • Two meetings to review and give feedback on the architect’s schematic drawings
    • Initial meeting with Principals and Transportation to examine boundaries
  • Spring 2014
    • Architect and Contractor named

The new school will have the following features:

  • 4 kindergarten classrooms
  • 14 classrooms
  • 5 resource/special care areas
  • Student project areas
  • Music room
  • Performing arts class
  • Double gym/change rooms
  • 4 kindergarten classrooms
  • 14 classrooms
  • 5 resource/special care areas
  • Student project areas
  • Music room
  • Performing arts class
  • Double gym/change rooms

Next Steps:

  • Parent Open House for Quispamsis Middle and individual meetings for the elementary schools.
  • Fall 2014
    • Boundaries finalized after parent meetings
    • Naming of the new school – committee will be formed (DEC member, District Staff person, Dept. Staff person, a community rep named by the DEC)
    • QMS Field ready for September 2014
  • Winter 2015
    • New Principal hired January 2015
  • Fall 2015
    • New school open September 2015

  Subscribe to Updates by Email

 

Determine School Based on Street Name

 
 

New School Boundary Map